Mechanic's liens in Texas: owners, contractors & lenders

Mechanic's liens in Texas: owners, contractors & lenders

Kenny Ramos, Esq., author

Written by

Written by

Kenny Ramos, Esq

Kenny Ramos, Esq

6

6

min read

min read

Table of Contents
Stone columns of a Texas courthouse

A mechanic's lien is the tool Texas law gives contractors, subcontractors, and suppliers to secure payment for work that improves real property. When the lien is properly perfected, it attaches to the property itself, and the owner may find that title cannot be conveyed or refinanced until the claim is resolved.

Texas has one of the more technical lien statutes in the country. Chapter 53 of the Texas Property Code sets strict deadlines for notices and affidavits, and the deadlines differ for original contractors, subcontractors, residential projects, and commercial projects. A claimant who misses a notice by a single day may lose the lien entirely, and an owner who ignores a timely notice may end up paying twice for the same work.

Whether you are an owner who has received a lien affidavit, a contractor who has not been paid, or a lender funding a project, the questions are the same: was the lien perfected, what does it attach to, and how is it enforced or removed. Below is an outline of each.

For contractors and suppliers: perfecting the lien

An original contractor with a direct contract with the owner perfects a lien by recording a lien affidavit in the county where the property sits, generally by the fifteenth day of the fourth month after the month the contract was completed, terminated, or abandoned, with a shorter deadline of the third month for residential projects. Subcontractors and suppliers must first send written notice of the unpaid amount to the owner and the original contractor by the fifteenth day of the third month after each month in which labor or materials were furnished, and then record the affidavit. The affidavit must be sworn, must describe the property and the work, and must be served on the owner within five days of recording. Errors in any of these steps are the most common reason a lien fails.

For owners: responding to and removing a lien

An owner who receives a subcontractor's notice should withhold, or retain, funds from the original contractor in the amount claimed, because payment to the contractor after notice does not protect the owner against the subcontractor's lien. Texas also requires the owner to hold back ten percent of the contract price for thirty days after completion as statutory retainage, which creates a fund for lien claimants. If a lien has been recorded, the owner can demand that the claimant file suit within a set period, can file a summary motion to remove an invalid lien, or can post a bond to indemnify against the lien so that the property is released and the dispute moves to the bond. A lien claimant who records a lien that is fraudulent or grossly inflated faces statutory liability.

For lenders: protecting the loan

A construction lender's deed of trust generally has priority over mechanic's liens only if it was recorded before the work began, and a lien claimant may argue that visible work on the site started earlier than the lender believes. Lenders should review lien waivers, payment applications, and contractor agreements before each disbursement, use the statutory conditional and unconditional waiver forms, and consider joint checks or direct payment to subcontractors where the general contractor's payment record is uncertain. Even where the lender has no contract with the claimant, a recorded lien clouds title, delays closing, and can force a payoff at sale. Diligence at each draw is the lender's best protection.

Residential projects have shorter deadlines

Texas treats work on a homestead differently from commercial work. A contractor who improves a homestead must have a written contract signed by both spouses before the work begins, and for certain projects the contract must be recorded, or the lien will not attach. The notice deadlines for subcontractors on residential projects are one month shorter than on commercial projects, and the affidavit must be recorded by the fifteenth day of the third month rather than the fourth. Contractors who work on both kinds of projects should keep two calendars, because a notice that is timely on a commercial job can be late on a house.

Lien waivers and the statutory forms

Texas prescribes the exact wording of lien waivers, and a waiver that does not follow the statutory form is unenforceable. There are four forms: conditional and unconditional waivers on progress payment, and conditional and unconditional waivers on final payment. An owner or lender should collect the correct waiver with each payment and should not accept an unconditional waiver until the payment has actually cleared. A contractor should not sign an unconditional waiver in exchange for a check that has not yet been honored, because the waiver releases the lien even if the check bounces.

Removing or bonding around a lien

An owner who believes a lien is defective has several options. A summary motion to remove the lien asks the court to decide, on an expedited basis, whether the claimant met the statutory requirements, without deciding whether the underlying debt is owed. A bond to indemnify against the lien, recorded with the county clerk, releases the property and substitutes the bond as security, which allows a sale or refinance to close while the dispute continues. An owner may also send a demand that the claimant file suit within a set period, after which an unenforced lien can be released. Which path is best depends on the size of the claim, the strength of the defect, and whether a closing is pending.

Enforcement and the deadline to sue

A perfected lien does not pay itself. The claimant must file suit to foreclose the lien, generally within one year after the last day the claimant could have recorded the affidavit, or within one year after completion on a residential project, and the deadline is shorter if the owner serves a demand. The suit is brought in the county where the property sits and typically joins the owner, the original contractor, and any lender with a recorded interest. Many lien disputes settle once suit is filed, because the lien clouds title and the owner has an incentive to resolve it before a sale or refinance.

Frequently asked questions

Can a supplier who sold materials to a subcontractor file a lien?
Yes, if the supplier sends the required notices to the owner and the original contractor on time and records the affidavit. Suppliers two tiers below the owner have the same rights as subcontractors but must send an additional notice.

Does an owner have to pay twice?
An owner who receives a timely notice from a subcontractor and nonetheless pays the original contractor may have to pay the subcontractor as well. Withholding the amount claimed, and holding statutory retainage, protects the owner.

What if the affidavit has a mistake in the property description?
Minor errors are often forgiven if the description still identifies the property, but a description that points to the wrong tract can invalidate the lien. Affidavits should be checked against the deed records before recording.

Can a lien be filed against public property?
No. Public projects in Texas are covered by payment bonds rather than liens, and claims must be made against the bond under a separate set of notice rules.

Key Takeaways

  • A perfected mechanic's lien attaches to the property, and Texas deadlines for notices and affidavits are strict.

  • Subcontractors and suppliers must give timely notice to the owner before recording; owners who receive notice should retain funds.

  • Owners can remove an invalid lien by summary motion or release the property by posting a bond.

  • Lenders protect priority by recording before work begins and by collecting proper waivers at every draw.

Attorney and client shaking hands after a consultation

Engage an attorney

Engage an attorney

Schedule a confidential consultation to review your transaction or dispute.

Schedule a confidential consultation to review your transaction or dispute.

( GET STARTED )

Let’s begin in the experience.

Professionals walking through a modern office lobby

( GET STARTED )

Let’s begin in the experience.

Professionals walking through a modern office lobby